Construction of Kashagan Gas Processing Plant to be completed in December 2026
Region
- 07 November, 2025
- 14:19
Construction of the Kashagan gas processing plant (GPP) will be completed in December 2026, said Alibek Zhamauov, chairman of the Board of QazaqGaz, Report informs referring to Kazakh media.
Equipment deliveries are expected to be completed in July 2026, and construction and installation of the integrated gas treatment facility is scheduled for October 2026.
He also cited gas export data for the first nine months of 2025, noting that Kazakhstan exported 3.9 billion cubic meters of gas. This exceeded the forecast by 28%. Domestic gas sales volumes were 100% fulfilled, reaching 13.6 billion cubic meters.
Latest News
09:37
US to watch fuel prices to prevent artificial hikes
Energy09:28
Deadly landslide claims 10 lives in PNG's East New Britain, local media report
Other09:11
Key indicators of world commodity, stock, and currency markets (16.04.2026)
Finance08:55
Dollar hangs near six-week lows as investors bet on Iran peace deal
Economy23:56
Norway and Netherlands ramp up drone funding for Ukraine
Other countries23:51
UK disburses final tranche to Ukraine via G7 revenue acceleration plan
Other countries23:37
Pentagon steps up planning for possible Cuba operations
Other countries23:15
Iran insists on Pakistan venue for talks with US
Foreign policy23:03