Azerbaijan Railways talks on Aghdam-Khankandi railway line progress

Infrastructure
  • 06 January, 2026
  • 14:05
Azerbaijan Railways talks on Aghdam-Khankandi railway line progress

The design of the Aghdam-Khankandi railway line in Azerbaijan is 81% complete, with construction and installation work 29% complete, Report informs referring to Azerbaijan Railways.

The total length of the railway line is 28 kilometers, or 30.8 kilometers including sidings.

The project includes the construction of three stations – Asgaran, Khojaly, and a railway and bus station complex in Khankandi. In addition, 124 engineering structures are planned.